Project name | Construction of the airport complex «Armavir» |
Industry classification | Transport |
Basic information about the project |
---|
Project essence | For cargo air transportation based on the runway of the airfield "Armavir-Central aviation facilities and Armavir flight training centre, the city of Armavir is a project of construction of the airport complex «Armavir». |
Project capacity | Estimated passenger traffic amounts to 150 thousand. persons/year. The annual volume of cargo transportation on FLIGHTS up to 3 thousand. tons. The annual volume of freight traffic on the MVL to 30 thousand. tons. |
Consumer market description | Natural or legal persons using the services of passenger and cargo transportation on domestic and foreign flights. |
Object construction term | 1.50 |
Competitive advantage | Advantageous geographical location of planned object. Suitable climatic conditions, in contrast to Stavropol airport in the autumn-winter period is almost always closed because of fog. 320 sunny days a year-the maximum figure for Russia. |
Resource availability for project realization | Construction of the airport complex is planned to be implemented in the territory of Krasnodar region, town of Armavir, Armavir flight training center "Krasnodar VVAUL". |
Planned volume of resource consumption (annual) |
---|
Planned volume of electricity consumption (annual), MWh | 30.00 |
Planned volume of gas consumption (annual), million cubic meters | |
Planned volume of water consumption (annual), million cubic meters | |
Degree of project development | Developed business plan, formed the plot of land |
Financial estimation of the project |
---|
Total cost of the project, mln rubles | 387 |
Own resources, million rubles | 387 |
Means of regional (municipal) budget, million rubles | |
Previously involved means, million rubles | |
Investment capacity, mln rubles | 387.00 |
Conditions of investor participation | Direct investments |
Form of investments return | The Monetary |
Payback period | 2.90 |
Basic indicators of investment project economic efficiency |
---|
Net present value (NPV) | 222.77 |
Simple payback time | 3.00 |
Discounted payback period | 3.50 |
Internal rate of return (IRR) | 67.90 |
Productivity index (PI) | 1.40 |
Income per year | 7780.79 |
Social efficiency of investment project |
---|
Number of workplaces | 155 |
Salary average level (thousand rub per year) | 432.00 |
Budgetary efficiency of investment project |
---|
Mid-annual tax payments, million rubles | 204.89 |
which includes into consolidated budget of the krai, million rubles | 66.63 |
General information about the ground area |
---|
Address of the area | Armavir, UL. Vorovskogo, (military aviation training center and Garden Association "Bloom"). |
Cadastre account of ground area | Not registered |
Cadastre number of area/of quarter | 23380105004 |
Declared area (m2) | 25000.00 |
Limit size of the area (m2) | 25000.00 |
Land category | Lands of inhabited localities |
Kind of allowed use | Production |
Actual use | Land plot is free of any buildings |
Availability of buildings, structures, constructions | Land plot is free of any buildings |
Permits, town-planning documentation | - Rules of land use and development, approved by the Decision of Armavir municipal Duma "About the statement of rules of land tenure and building of municipal formation town of Armavir," from August 27 2015 No. 792 (Rev. from 20 may 2016, No. 134). |
Information about proprietor (right holder) |
---|
Proprietor | Municipal property |
Right holder | Administration of municipal formation Armavir town |
Kind of right | Another |
Information about encumbrance and limitation |
---|
Kind of encumbrance, limitation | There Are No |
Encumbrance area | |
Electricity supply |
---|
Power supply center (name, right-holder) | OAO «nesk-socket Armavirelektroseti ". |
Power supply center (electrotension class) | Middle class of tension – from 1 kV to 35 kV |
Power supply center (free power (MWt)) | 0.50 |
Power supply center (distance(m)) | 214.00 |
Nearest connection point (network tension, kV) | 6.00 |
Nearest connection point (distance(m)) | 214.00 |
Gas-supplying |
---|
Gas pipeline (name, right-holder) | Jsc "Armavirgorgaz" |
Gas pipeline (diameter(mm)) | 114.00 |
Gas pipeline (pressure(MPa)) | Average pressure pipelines – from 0,005 to 0,3 |
Gas pipeline (carrying capacity(cube. m.in a year)) | 1142574.00 |
Gas pipeline (distance(m)) | 213.00 |
Nearest connection point (diameter(mm)) | 114.00 |
Nearest connection point (pressure (MPa)) | Average pressure pipelines – from 0,005 to 0,3 |
Nearest connection point (carrying capacity (cubic meter a year)) | 1142574.00 |
Nearest connection point (distance(m)) | 213.00 |
Water-supply |
---|
Water supply source (name, right-holder) | GUP KK «SVVUK Kurganinsky group plumbing » |
Water supply source (power (cubic meters a day)) | 50.00 |
Water supply source (quality of water) | Drinking water |
Water supply source (distance(m)) | 523.00 |
Nearest connection point (power (cubic meters a day)) | 50.00 |
Nearest connection point (diameter(mm)) | 400.00 |
Nearest connection point (distance(m)) | 523.00 |
Sewage system |
---|
Type of building (name, right-holder) | GUP KK «SVVUK Kurganinsky group plumbing » |
Type of building (power (cubic meters a day)) | 50.00 |
Type of building (distance(m)) | 520.00 |
Nearest point of connection (power (cubic meters a day)) | 50.00 |
Nearest point of connection (diameter(mm)) | 200.00 |
Nearest point of connection (distance(m)) | 520.00 |
Installation of telephones/internet |
---|
Central network (distance(m)) | |
Mobile communication (distance(m)) | |
Rated price of the ground area supplying with engineering, mln.rub | 20.62 |
Distance to the large settlements and objects of a transport infrastructure |
---|
Remoteness from | Name | Distance (km) |
---|
center of municipal formation | The central part of the town of Armavir | 2.70 |
nearest settlement | The Town Of Novokubansk | 16.00 |
Center of federal subject | Krasnodar city | 250.00 |
highways (regional, federal value) | MOTORWAY "Kavkaz" | 7.80 |
highways of local value | "Entrance to the city of Armavir" | 0.50 |
nearest railway station | Railway station «Armavir-1» Railway station «Àrmavir-2» | 3.60 |
nearest railway | - | 2.90 |
airport | Krasnodar airport | 200.00 |
seaport | seaport Novorossiysk | 360.00 |
Additional information about the ground area |
---|
Special conditions | Site with capacity collapsible soil thicknesses more than 5 m. loams of the top horizon 1-7m, the bottom horizon 3-10m, underlain by gravel-pebble deposits with sandy filler. Seismicity of 7 points. |
Cost of rent/buy of the ground area, mln. rub | |
Geographical coordinates of object (dd.dddddd) |
---|
Latitude (N) | 44.982217 |
Longitude (E) | 41.096770 |
Notes | Plots are available from bidding, the rent is calculated on the basis of market value. |
Data on the project initiator (in case of existence information about the legal/physical person) |
---|
Name / Full name | Administration of municipal formation Armavir town |
Postal address | 352900, Krasnodar region, town of Armavir, UL. Karl Liebknecht, 52 |
Site | www.armawir.ru |
Phone/fax | 86137-2-74-70 |
E-mail address | info@armawir.ru |
Data about the applicant (executive authority/local government executive authority) |
---|
Name | Administration of municipal formation Armavir town |
Postal address | 352900, Krasnodar region, town of Armavir, UL. Karl Liebknecht, 52 |
Site | www.armawir.ru |
Phone/fax | 86137-2-74-70 |
E-mail address | info@armawir.ru |
Executive (Full name, work position, phone number) | Lavrentsova Elena |